A firm whose cost of capital is 10% considering two projects X & Y. The details are

9.84K views
0

A firm whose cost of capital is 10% considering two projects X & Y. The details are

X                Y

Investment           70000                   70000

Cash inflow          1st     10000                   50000

2nd     20000                   40000

3rd      30000                   20000

4th      45000                   10000

5th      60000                   10000

Compute the NPV at 10%, P.I and IRR for the two projects

0

NPV Method

NPV of Project X

Year            cash inflow PV of Rs. 1                    PV of cash inflow

                                      10%                                                           

1                 10000                   0.909                    9090

2                 20000                   0.826                    16520

3                 30000                   0.751                    22530

4                 45000                   0.683                    30735

5                 60000                   0.621                    37260

Total cash inflow                                        116135

– PV of initial investment                           70000

46135

NPV = Rs. 46135

NPV of Project Y

Year cash inflow PV of of Rs.1       PV of cash inflow

                             At 10%                                            

1        50000                   0.909                    45450

2        40000                   0.826                    33040

3        20000                   0.751                    15020

4        10000                   0.683                    6830

5        10000                   0.621                    6210

Total cash inflow                              106550

Less PV of initial investment            70000

NPV                                                  36550

NPV = Rs. 36550

NPV is greater for project X . So we select project X.

 

 

 

Profitability index for project X

                   = PV of cash inflow

PV of cash outflow

= 116135 = 1.66

70000

For project Y

= 106550    = 1.52

70000

PI is greater for project X. So we select project X.

IRR method

For project X

Year  cash inflow PV factor    discounted PV at 30%  discounted

                             At 25%       cash inflow                    cash inflow

1        10000                   0.8              8000           0.769          7690

2        20000                   0.640          12800                   0.592          11840

3        30000                   0.512          15360                   0.455          13650

4        45000                   0.410          18450                   0.350          15750

5        60000                   0.328          19680                   0.269          16140

74290                                      65070

IRR for project X

25 + 74290 – 70000  x 5

74290 – 65070

= 27.32 %

 

 

 

 

 

 

For Project Y

Year  cash inflow           PV at 35%  discounted  PV at 40%  discounted

                                                Cash flow                      cash flow

  1. 50000 0.769          38450                   0.714          35700

2        40000                   0.592          23680                   0.510          20400

3        20000                   0.455          9100           0.364          7280

4        10000                   0.350          3500           0.260          2600

5        10000                   0.269          2690           0.186          1860

72370                                      67840

IRR = 35 + 72370 – 70000   x 5  = 37.61%

72370 – 67840

You are viewing 1 out of 0 answers, click here to view all answers.

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved