calculate the projects expected NPV, standard deviation, and coefficient of variation

4.93K views
0

Huang Industries is considering a proposed project whose estimated NPV is $12 million. this estimate assumes that exonomic conditions will be “average.” however, the CFO realizes that conditions could be better or worse, so she performed a scenario analysis and obtained these results:

economic scenario Probability of outcome NPV
recession 0.05 ($86 million)
below average 0.2.0 (14 million)
average 0.50 12 million
above average 0.20 24 million
boom 0.05 32 million

calculate the projects expected NPV, standard deviation, and coefficient of variation

0

Answer

expected NPV…sum all (probability of scenario * NPV if that scenario)

= 5.3 mil

Working notes for the above answer  is as under

Prbabelity NPV  
(A) (B) (A*B)
0.05 -86 -4.3
0.2 -14 -2.8
0.5 12 6
0.2 24 4.8
0.05 32 1.6
1   5.3

 

So NPV = 5.3 Million

(2)

std dev is sq rt of variance
variance = for each economic scenario…(NPV for that scenario – 5.3mil)^2 * probability of that scenario…then sum all

 

Prbabelity NPV NPV of
Project
     
(A) (B) (  C) D = (B-C) Square
of D
D*A
0.05 -86 5.3 -91.3 8335.69 416.7845
0.2 -14 5.3 -19.3 372.49 74.498
0.5 12 5.3 6.7 44.89 22.445
0.2 24 5.3 18.7 349.69 69.938
0.05 32 5.3 26.7 712.89 35.6445
          619.31

 

= 619.31,… sq rt (std dev)

= 24.8859
3
coeff of variation

= std dev / expected value

= 24.8859 / 5.3

= 4.6395

CV =4.695

 

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved