Compare the following 2 altrernatives using the Present Worth method

550 views
0

Compare the following 2 altrernatives using the Present Worth method

DRAW ALL CASH FLOW DIAGRAMS

RATE 3.5% per year for all problems unless otherwise noted

0

Answer:

We need to calculate Net prasent vale of both the alternative as follow

Alternative – A
  Year Construction
Cost
Benefit Total
Flow
Prasent
Valuue factor at 3.5%
 
    A B C = A+B D C*D
  0 -580,000   -580,000 1 -580000
  1   250,000 250,000 0.966184 241545.9
  2   250,000 250,000 0.933511 233377.7
  3   250,000 250,000 0.901943 225485.7
  4   250,000 250,000 0.871442 217860.6
  5   250,000 250,000 0.841973 210493.3
  6   250,000 250,000 0.813501 203375.2
  7   250,000 250,000 0.785991 196497.7
  8   250,000 250,000 0.759412 189852.9
            1138489

 

 

 

Alternative – B
  Year Construction
Cost
Benefit Total
Flow
Prasent
Valuue factor at 3.5%
 
    A B C = A+B D C*D
  0 -650,000   -650,000 1 -650000
  1   350,000 350,000 0.966184 338164.3
  2   350,000 350,000 0.933511 326728.7
  3   350,000 350,000 0.901943 315679.9
  4   350,000 350,000 0.871442 305004.8
  5   350,000 350,000 0.841973 294690.6
  6   350,000 350,000 0.813501 284725.2
  7   350,000 350,000 0.785991 275096.8
  8   350,000 350,000 0.759412 265794
            1755884

 

NPV Amount in $
Alternative – A 1138488.88
Alternative – B 1755884.44

 

Conclusion ; As we can see that NPV of the project B is more so you can choose Alternative B

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved