Complete the below table to calculate throughput time, manufacturing cycle efficiency (MCE), and delivery cycle time. for each month

1.94K views
0
MacIntyre Fabrications, Ltd., of Aberdeen, Scotland, has recently begun a continuous improvement campaign in conjunction with a move toward Lean Production. Management has developed new performance measures as part of this campaign. The following operating data have been gathered over the last four months:
Month
1 2 3 4
  Throughput time ? ? ? ?
  Manufacturing cycle efficiency ? ? ? ?
  Delivery cycle time ? ? ? ?
  Percentage of on-time deliveries 80% 81% 86% 93%
  Total sales (units) 10,470 10,580 10,470 10,480
      Management would like to know the company’s throughput time, manufacturing cycle efficiency, and delivery cycle time. The data to compute these measures have been gathered and appear below:
Month
1 2 3 4
  Move time per unit, in days 0.5 0.5 0.6 0.6
  Process time per unit, in days 0.8 0.7 0.4 0.6
  Wait time per order before start
of production, in days
9.8 8.0 5.0 4.0
  Queue time per unit, in days 3.0 3.0 3.0 1.0
  Inspection time per unit, in days 0.5 0.5 0.7 0.6
Required:
1. Complete the below table to calculate throughput time, manufacturing cycle efficiency (MCE), and delivery cycle time. for each month. (Round your answers to 1 decimal place.)
0

Complete the below table to calculate throughput time, manufacturing cycle efficiency (MCE), and delivery cycle time. for each month.

Month
1 2 3 4
Throughput time in days
Process time 0.6 0.5 0.5 0.4
Inspection Time 0.7 0.7 0.4 0.3
Move time 0.6 0.5 0.4 0.5
Queue Time 3.6 3.6 2.6 1.7
Total Through put time 5.4 5.3 3.9 2.9
Manufacturing cycle
efficiency (MCE)
11.10% 9.40% 12.80% 13.80%
Delivery cycle time in days
Wait time 9.6 8.7 5.3 4.7
Total throughput time 5.4 5.3 3.9 2.9
Total delivery cycle time 15 14 9.2 7.5

The general trend is favorable in all of the performance measures except for total sales. On-timeis up, process time is down, ispection time is down, move time is basically unchanged, queue timeis down, manufacturing cycle efficiency is up, and the delivery cycle time is down.

3.Refer to the move time, process time, and so forth, given for month 4. Assume that in month 5 the move time, process time, and so forth, are the same as for month 4, except that through the implementation of Lean Production, the company is able to completely eliminate the queue time during production in month 6 the move time, process time, and so forth, are the same as for month 5, except that the company is able to completely eliminate the inspection time. Compute the new throughput time and MCE. (Round your answers to 1 decimal place.)

Month
5 6
Throughput time in days
Process time 0.4 0.4
Inspection Time 0.3 0
Move time 0.5 0.5
Queue Time 0 0
Total Through put time 1.2 0.9
Manufacturing cycle
efficiency (MCE)
33.30% 44.40%

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved