Construction accounting under lFRS Appendix] In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows 2016 2017 2018 Cost incurred during the year $2,400,000 $3,600,000 $2,200,000 Estimated costs to complete as of year-end 5.600.000 2,000,000 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction reports under lFRS and concludes that the percentage-of-completion method is not appropriate Required 1. Calculate the amount of revenue and gross profit to be recognized in each of the three years.

4.38K views
0

Purchase answer in just $2

ask for the request in below link

http://www.smartstudyhelp.com/contactus.html

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved