For planning purposes, managers prefer to use

635 views
0
  1. For planning purposes, managers prefer to use

 

  1. actual rates for cost allocation because the rates are calculated from real amounts.
  2. actual rates for cost allocation because actual rates are easier to justify to users.
  3. budgeted rates for cost allocation because the rates are known in advance.
  4. budgeted rates for cost allocation because any variances are transferred to users.

 

0

budgeted rates for cost allocation because the rates are known in advance