If the required return is 10 percent, what is the NPV for each of these projects?

2.17K views
0
Garage, Inc., has identified the following two mutually exclusive projects:

 

Year Cash Flow (A) Cash Flow (B)
0 –$ 29,800 –$ 29,800
1 15,200 4,700
2 13,100 10,200
3 9,600 16,000
4 5,500 17,600

 

a-1 What is the IRR for each of these projects? (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16))

 

IRR
  Project A %
  Project B %

 

a-2 Using the IRR decision rule, which project should the company accept?
Project A
Project B
a-3 Is this decision necessarily correct?
Yes
No

 

b-1 If the required return is 10 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your final answers to 2 decimal places. (e.g., 32.16))

 

NPV
  Project A $
  Project B $
b-2 Which project will the company choose if it applies the NPV decision rule?
Project A
Project B

 

c. At what discount rate would the company be indifferent between these two projects? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16))

 

  Discount rate
0
Project A
0 29800
1 15200
2 13100
3 9600
4 5500

The formula for IRR is:

0 = P0 + P1/(1+IRR) + P2/(1+IRR)2 + P3/(1+IRR)3 + . . . +Pn/(1+IRR)n

IRR OF THE PROJECT A IS =20.36%

where P0, P1, . . . Pn equals the cash flows in periods 1, 2, . . . n, respectively; and
IRR equals the project’s internal rate of return.

Let’s look at an example to illustrate how to use IRR.

AsHere is how the IRR equation looks in this scenario:

0 = -$29800 + ($15200)/(1+.2036) + ($13100)/(1+.2036)2 + ($9600)/(1+.2036)3 + $5,500/(1+.2036)4

Year Project B
0 29800
1 4700
2 10200
3 16000
4 17600

IRR OF THE PROJECT B IS 18.46%

0 = -$29800 + ($15200)/(1+.1846) + ($13100)/(1+.1846)2 + ($9600)/(1+.1846)3 + $5,500/(1+.1846)4

IRR
  Project A 20.36%
  Project B 18.46 %

A-2

Using the IRR decision rule, which project should the company accept?

Project A is accepted because it has higher IRR

A-3

Is this decision necessarily correct? = Yes

If you look at IRR, you might be tempted to choose project A. But the IRR calculation implicitly assumes that the interim cash flows are invested at the same rate. But this assumption is not likely to be true. Interim cash flows are more likely to be invested at the required rate of return. So, use NPV to decide. Based on NPV you will choose project B.

NPV of the project A

Period Cash Flow Present Value
0 -29,800.00 -29,800.00
1 15,200.00 13,818.18
2 13,100.00 10,826.45
3 9,600.00 7,212.62
4 5,500.00 3,756.57
Total: 5,813.82

NPV of the project B

Period Cash Flow Present Value
0 -29,800.00 -29,800.00
1 4,700.00 4,272.73
2 10,200.00 8,429.75
3 16,000.00 12,021.04
4 17,600.00 12,021.04
Total: 6,944.55
NPV
  Project A $ 5813.82
  Project B $ 6944.55

B-2

Which project will the company choose if it applies the NPV decision rule?

Based on NPV you will choose project B.

You are viewing 1 out of 0 answers, click here to view all answers.

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved