Now, suppose that two companies are looking at the same project. Company “A” has a beta of 1.5 and a cost of capital of 25%. Company “B” has a beta of 0.8 and a cost of capital of 15%. When evaluated at a rate of 15%, the project shows an NPV of +$5 million, and when evaluated at a rate of 25%, the project shows an NPV of -$2 million. Should either company accept the project, and if so, under what conditions? Please explain your reasoning of how you came to the conclusion that you did

842 views
0

Now, suppose that two companies are looking at the same project. Company “A” has a beta of 1.5 and a cost of capital of 25%. Company “B” has a beta of 0.8 and a cost of capital of 15%. When evaluated at a rate of 15%, the project shows an NPV of +$5 million, and when evaluated at a rate of 25%, the project shows an NPV of -$2 million. Should either company accept the project, and if so, under what conditions?

Please explain your reasoning of how you came to the conclusion that you did

0

Answer:

We have been provided with the information as follow

Company A Company B
Beta 1.5 0.8
cost of capital 25% 15%

 

Here ,we can see that When evaluated at a rate of 15%, the project shows an NPV of +$5 million, and when evaluated at a rate of 25%, the project shows an NPV of -$2 million which clearly mean that company B should accept the project because it has lower Beta as well as lower cost of capital  which matches the return of the project so company B should accept the project

Here company A can only accept the project it its beta and cost of capital are getting lower line

You are viewing 1 out of 0 answers, click here to view all answers.

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved