Prepare a materials variance information table showing the standard price, the actual price, the standard quantity, and the actual quantity

2.80K views
0

The following data were drawn from the records of Kersten Corporation

  Planned volume for year (static budget)   5,000  units        
  Standard direct materials cost per unit   3.00  lbs. @ $ 1.80  per pound
  Standard direct labor cost per unit   3.80  hours @ $ 5.00  per hour
  Total expected fixed overhead costs $ 20,000          
  Actual volume for the year (flexible budget)   5,500  units        
  Actual direct materials cost per unit   2.50  lbs. @ $ 2.20  per pound
  Actual direct labor cost per unit   4.20  hrs. @ $ 4.40  per hour
  Total actual fixed overhead costs $ 16,300          
 

 

Required:

 

a. Prepare a materials variance information table showing the standard price, the actual price, the standard quantity, and the actual quantity. (Round “Standard price” and “Actual price” to 2 decimal places.)

 

   

 

b. Calculate the materials price and usage variances. Indicate whether the variances are favorable (F) or unfavorable (U). (Select “None” if there is no effect (i.e., zero variance).)

 

   

 

c. Prepare a labor variance information table showing the standard price, the actual price, the standard hours, and the actual hours. (Round “Standard price” and “Actual price” to 2 decimal places.)

 

   

 

d. Calculate the labor price and usage variances. Indicate whether the variances are favorable (F) or unfavorable (U). (Select “None” if there is no effect (i.e., zero variance).)

 

   

 

e. Calculate the predetermined overhead rate, assuming that Kersten uses the number of units as the allocation base. (Round your answer to 2 decimal place.)

 

   

 

f. Calculate the fixed cost spending variance. Indicate whether the variance is favorable (F) or unfavorable (U). (Select “None” if there is no effect (i.e., zero variance).)
0

Answer:

A
Material variance information statement
Slandered price Per pond 1.8
Actual price Per pond 2.2
Standard Quantity for flexible Budget
(5500*3 lbs)= 16500
16500
Actual Quantity for flexible Budget
(5500*2.5 lbs)= 13750
13750

Material Price Variance

= (Standard Price- − Actual Price) × Actual Quantity

=(1.8-2.2) *13750

=0.4*5500

=5500 U

Material Usage Variance

= (Actual usage – Standard usage) x Standard cost per unit

=(13750-16500) *2.2

=4950F

 

C
Labor variance information statement
Standard price Per Hour 5
Actual price Per Hour 4.4
Standard Quantity for flexible Budget
(5500*3.8 fr)= 20900
20900
Actual Quantity for flexible Budget
(5500*4.2)= 23100
23100

 

D

Labor Price Variance

= (Standard Price- − Actual Price) × Actual hour

=(5-4.4) *23100

=13860F

 

Labor Usage Variance

= (Actual hours – Standard hours) x Standard rate

=(23100-20900)*5

=2200*5

=11000 U

E
Fixed overhead  information statement
Standard 20000
Actual price 16300

 

 

 

Fixed Overhead Volume Variance = Applied Fixed Overhead – Budgeted Fixed Overhead

= Applied Fixed Overhead = Standard Fixed Overhead Rate × Standard Hours Allowed

Standard Fixed Overhead Rate = Budgeted Fixed Overhead
Budgeted Units

 

=20000/5000

=4

Applied Fixed Overhead = 5500 × $4

= $22,000

=22000-20000

=2000 U

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved