Prepare a performance report that compares budgeted and actual costs for the period just ended

983 views
0

Midwest Ventilation, Inc., produces industrial ventilation fans. The company plans to manufacture 81,000 fans evenly over the next quarter at the following costs: direct material, $1,944,000; direct labor, $324,000; variable production overhead, $522,450; and fixed production overhead, $948,000. The fixed-overhead amount includes $78,000 of straight-line depreciation and $120,000 of supervisory salaries. Shortly after the conclusion of the quarter’s first month, Midwest reported the following costs:

Direct material $ 585,500

Direct labor 94,500

Variable production overhead 178,000

Depreciation 26,000

Supervisory salaries 40,800

Other fixed production overhead 245,000

Total $ 1,169,800

Dave Kellerman and his crews turned out 23,000 fans during the month—a remarkable feat given that the firm’s manufacturing plant was closed for several days because of storm damage and flooding. Kellerman was especially pleased with the fact that overall financial performance for the period was favorable when compared with the budget. His pleasure, however, was very short-lived, as Midwest’s general manager issued a stern warning that performance must improve, and improve quickly, if Kellerman had any hopes of keeping his job.

Required: 2. Which of the two budgets would be more useful when planning the company’s cash needs over a range of activity?

Flexible Budget or Static Budget????

  1. Prepare a performance report that compares budgeted and actual costs for the period just ended
0

Answer:

First of all let us understand the meaning of both the budget.

Static Budget:A static budget is based on a single expected level of activity.

Flexible buget

On the other hand, a flexible budget is based on data for several levels of activity

Which one is Useful:

. The flexible budget because it incorporates different activity levels

Question

Prepare a performance report that compares budgeted and actual costs for the period just ended

Answer:

  Static Budget
23000 units
Actual Variance  
Direct material 552000 585500 -33500 U
Direct labor 92000 94500 -2500 U
Variable production overhead 148350 178000 -29650 U
Depreciation 26000 26000 0  
Supervisory salaries 40000 40800 -800 U
Other fixed production overhead 316000 245000 71000 F
Total 1174350 1169800 4550 U

 

Working notes for the above answer is as under

Explaination for above calculation   Per Unit
Direct material 1944000/81000 24
Direct labor 324000/81000 4
Variable production overhead 522450/81000 6.45
Depreciation 78000/3 26000
Supervisory salaries 120000/3 40000
Other fixed production overhead 948000/3 316000
You are viewing 1 out of 0 answers, click here to view all answers.

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved