Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2017, 10,700 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 12,500 direct labor hours. All materials purchased were used.

1.09K views
0

Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2017, 10,700 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 12,500 direct labor hours. All materials purchased were used.

Cost Element Standard (per unit) Actual
Direct materials 9 yards at $4.80 per yard $456,840 for 97,200 yards ($4.70 per yard)
Direct labor 1.20 hours at $13.00 per hour $182,776 for 13,640 hours ($13.40 per hour)
Overhead 1.20 hours at $6.50 per hour (fixed $3.70; variable $2.80) $48,400 fixed overhead $36,500 variable overhead

Overhead is applied on the basis of direct labor hours. At normal capacity, budgeted fixed overhead costs were $46,250, and budgeted variable overhead was $35,000.

A: Compute the total, price, and quantity variances for (1) materials and (2) labor. (Round answers to 0 decimal places, e.g. 125.)

TOTAL MATERIALS VARIANCE $ Favorable/Unfavorable/Neither
MATERIALS PRICE VARIANCE —— Favorable/Unfavorable/Neither
MATERIALS QUANTITY VARIANCE —— Favorable/Unfavorable/Neither
TOTAL LABOR VARIANCE —— Favorable/Unfavorable/Neither
LABOR PRICE VARIANCE —— Favorable/Unfavorable/Neither
LABOR QUANTITY VARIANCE —— Favorable/Unfavorable/Neither

B: Compute the total overhead variance.

Total overhead variance $____________ Favorable/Unfavorable/Neither

0

Purchase answer in just $5

ask for the request in below link

http://www.smartstudyhelp.com/contactus.html

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved