Shatner Inc. has decided to use the high-low method to estimate the total cost and the fixed and variable cost components of the total cost. The data for various levels of production are as follows: Units Produced Total Costs 1,980 $380,160 3,630 466,330 5,280 591,360 a. Determine the variable cost per unit and the total fixed cost. Variable cost: (Round to the nearest dollar.) $ per unit Total fixed cost: $ b. Based on part (a), estimate the total cost for 2,610 units of production. Total cost for 2,610 units:

780 views
0

Shatner Inc. has decided to use the high-low method to estimate the total cost and the fixed and variable cost components of the total cost. The data for various levels of production are as follows:

Units Produced Total Costs
1,980 $380,160
3,630 466,330
5,280 591,360

a. Determine the variable cost per unit and the total fixed cost.

Variable cost: (Round to the nearest dollar.) $ per unit
Total fixed cost: $

b. Based on part (a), estimate the total cost for 2,610 units of production.

Total cost for 2,610 units:
0

Purchase answer in just $2

ask for the request in below link

http://www.smartstudyhelp.com/contactus.html

You are viewing 1 out of 1 answers, click here to view all answers.

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved