The following information was obtained from the records of a manufacturing unit using Standard Costing System:

1.08K views
0

The following information was obtained from the records of a manufacturing unit using Standard Costing System:

 

  Budgeted Actual
Production per month 2,500 units 2,000 units
Assume 8 hours/day    
Working days 25 26
Fixed overhead $50,000 $45,000
Variable overhead $15,000 $15,000

 

Required:

 

To calculate the following overhead variance.

(a)        Variable overhead variance

(b)       Fixed overhead variance

 

0

Solution:

 

Working hours available/day = 25 x 8 = 200 hours

Standard time =  = 0.08 hr/unit

Variable overhead absorption rate = Budgeted variable overhead
Planned production in standard hours
= $15,000 / 200 hours
= $75/hour

 

Fixed overhead absorption rate = Budgeted fixed overhead
Planned production in standard hours
= $50,000 / 200 hours
= $250/hour

 

(a) (i) Variable overhead cost variance  

=

 

SVO – AVO

  = 75 x 0.08 x 2,000 – 15,000
  = 12,000 – 15,000
  = $3,000 (A)

 

(a) (ii) Variable overhead expenditure variance  

=

 

(SVOR – AVOR) x AH

  = 75 x 26 x 8 – 5,000
  = 15,600 – 15,000
  = $600 (F)

 

(a) (iii) Variable overhead efficiency variance  

=

 

(SH – AH) x SVOR

  = (2,000 x 0.08 – 208) x 75
  = $3,600 (A)

 

(b) (i) Fixed overhead cost variance = AbFO – AFO
  = (250 x 0.08 x 2,000) – 45,000
  = 40,000 – 45,000
  = $5,000 (A)

 

(b) (ii) Fixed overhead expenditure variance  

=

 

BFO – AFO

  = 50,000 – 45,000
  = $5,000 (F)

 

(b) (iii) Fixed overhead volume variance  

=

 

AbFO – BFO

  = 250 x (0.08 x 2,000) – 50,000
  = 40,000 – 50,000
  = $10,000 (A)

 

(b) (iv) Fixed overhead efficiency variance =

=

AbFO – SFO

FOAR x Actual labour hours worked – FOAR x standard hours for actual output

  = 250 x 26 x 8 – 250 x 0.08 x 2,000
  = 12,000 (A)

 

(b) (iv) Fixed overhead capacity variance =

=

AbFO – BFO

FOAR x Actual labour hours worked – Budgeted fixed overhead

  = 250 x 26 x 8 – 50,000
  = 52,000 – 50,000
  = 2,000 (F)