The Parco Company applies manufacturing overhead costs to products on the basis of direct labor-hours. The standard cost card shows that 12 direct labor-hours are required per unit of product. For August, the company budgeted to work 360,000 direct labor-hours and to incur the following total manufacturing overhead costs:

729 views
0

The Parco Company applies manufacturing overhead costs to products on the basis of direct labor-hours. The standard cost card shows that 12 direct labor-hours are required per unit of product. For August, the company budgeted to work 360,000 direct labor-hours and to incur the following total manufacturing overhead costs:

 

Total variable overhead costs $396,000
Total fixed overhead costs $475,200
   

During August, the company completed 28,000 units of product, worked 344,000 direct labor-hours, and incurred the following total manufacturing overhead costs:

 

Total variable overhead costs $395,600
Total fixed overhead costs $461,200
   

The denominator activity in the predetermined overhead rate is 360,000 direct labor-hours. What is the fixed overhead volume variance for August?

0

First, compute the fixed overhead (FOH) rate as follows:

Budgeted fixed overhead costs ÷ budgeted direct labor hours = FOH rate

$475,200 ÷ 360,000 direct labor hours = $1.32 per direct labor hour

Volume variance = Budgeted fixed overhead – Fixed overhead applied

Volume variance = Budgeted fixed overhead – (Standard hours allowed x FOH rate)

Volume variance = $475,200 – (((28,000 units x 12) x $1.32)

Volume variance = $475,200 – (336,000 x $1.32)  = $475,200 – $443,520 = $31,680 U

 

Since budgeted fixed overhead was more than the amount applied to work in process during the period, the volume variance is unfavorable

You are viewing 1 out of 0 answers, click here to view all answers.

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved