we have been provided with the cash flow of the two project and we need to calculate IRR.
Calculation of the IRR ( internal rates of return) of project -A is as follow
IRR = -250 +130/ (1+r)1+130/ (1+r)02+130/ (1+r)3+130/ (1+r)4
Solving this equation by trial and error method you will get
IRR=0.3741
IRR= 37.41%
Calculation of the IRR ( internal rates of return) of project -B is as follow
IRR = -250 +150/ (1+r)1+150/ (1+r)02+150/ (1+r)3
Solving this equation by trial and error method you will get
IRR=0.3630
IRR= 36.30%
Project
IRR
Project-A
37.41%
Project-B
36.30%