What are the internal rates of return on projects A and B?

472 views
0
The following are the cash flows of two projects:

 

Year Project A Project B
0 $   -250 $   -250
1 130 150
2 130 150
3 130 150
4 130
What are the internal rates of return on projects A and B? (Enter your answers as a percent rounded to 2 decimal places.)
                  Project IRR
A ____%
B  ____%
0

we have been provided with the cash flow of the two project and we need to calculate IRR.

Calculation of the IRR ( internal rates of return) of project -A is as follow

 

IRR = -250 +130/ (1+r)1+130/ (1+r)02+130/ (1+r)3+130/ (1+r)4

Solving this equation by trial and error method you will get

IRR=0.3741

IRR= 37.41%

Calculation of the IRR ( internal rates of return) of project -B is as follow

IRR = -250 +150/ (1+r)1+150/ (1+r)02+150/ (1+r)3

Solving this equation by trial and error method you will get

IRR=0.3630

IRR= 36.30%

Project
IRR

Project-A
37.41%

Project-B
36.30%