What is each project’s payback period? If the cutoff period is 3 year, then which project would you choose? What is each project’s discounted payback period? If the cutoff period is 3 year, then which project would you choose?

1.03K views
0

ou are evaluating two mutually exclusive projects with the following net cash flows:

Project X    Project Y

Year     Cash Flow     Cash Flow

0       -$1000               -$1100

1            100                   1000

2            300                     100

3            400                     150

4            700                       50

The cost of capital is 12 percent.

What is each project’s payback period? If the cutoff period is 3 year, then which project would you choose?

 

What is each project’s discounted payback period? If the cutoff period is 3 year, then which project would you choose?

 

What is each project’s NPV? Which project would you choose based on NPV rule?

 

What is each project’s IRR? Which project would you choose based on IRR rule?

 

What is each project’s profitability index? Based on profitability index, which project is preferred?

 

What is each project’s equivalent annual annuity (EAA)? Based on EAA, which project is preferred?

0
Payback
Year Project X Incremental
Cash flow
0 -1,000
1 100 100
2 300 400
3 400 800
4 700 1,500
Year Project y Incremental
Cash flow
0 -1100
1 1000 1000
2 100 1,100
3 150 1,250
4 50 1,300

If we consider payback method project y has earlier payback then the project X so the company should accept projrct y

If the cutoff period is 3 year, then which project would you choose?

then also company should choose project Y

What is each project’s discounted payback period? If the cutoff period is 3 year, then which project would you choose?

Discounted   Payback
Year Project X Discount Factor
@ 12%
pv Incremental
Cash flow
1 100 0.89286 89.28571429 89.28571429
2 300 0.79719 239.1581633 328.44388
3 400 0.71178 284.7120991 613.15598
4 700 0.63552 444.8626549 1,058.01863

in the three year we recover 613. dollar so remaning 386 we have to recover in the year 4

= 386.84 *365/ 444.1058

=318 days

Total paybeck = 3 year and 318 days

Year Project y Discount Factor
@ 12%
pv Incremental
Cash flow
1 1000 0.89286 892.8571429 892.8571429
2 100 0.79719 79.71938776 972.57653
3 150 0.71178 106.7670372 1,079.34357
4 50 0.63552 31.77590392 1,111.11947

in the three year we recover 1079. dollar so remaning 386 we have to recover in the year 4

= 20 *365/ 31.77

=237 days

If we consider payback method project y has earlier payback then the project X so the company should accept projrct y

If the cutoff period is 3 year, then which project would you choose?

then also company should choose project Y

Total paybeck = 3 year and 237 days

What is each project’s NPV? Which project would you choose based on NPV rule?

Net prasent value
Year Project X Discount Factor
@ 12%
pv
0 -1000 1 -1000
1 100 0.89286 89.28571429
2 300 0.79719 239.1581633
3 400 0.71178 284.7120991
4 700 0.63552 444.8626549
58.01863156
Year Project y Discount Factor
@ 12%
pv
0 -1100 1 -1100
1 1000 0.89286 892.8571429
2 100 0.79719 79.71938776
3 150 0.71178 106.7670372
4 50 0.63552 31.77590392
11.1194717

Based on the NPV we should choose projrct X becase it hase higher NPV then the project Y

What is each project’s IRR? Which project would you choose based on IRR rule?

the formulla of IRR is

0 = P0 + P1/(1+IRR) + P2/(1+IRR)2 + P3/(1+IRR)3 + . . . +Pn/(1+IRR)n

Project x

0 = -$1000 + ($100)/(1+IRR)+ ($300)/(1+IRR.)2 + ($400)/(1+IRR)3 + $700/(1+IRR)4

Project Y

0 = -$1100 + ($1000)/(1+IRR)+ ($100)/(1+IRR.)2 + ($150)/(1+IRR)3 + $50/(1+IRR)4

Using trial and error method we have found IRR =

Project x 14.11%
Project y 12.84%

Baseed on IRR , We should chose project Y because it hase higher IRR i.e 12.84%

What is each project’s profitability index? Based on profitability index, which project is preferred?

NPv Invest ment P.I P. I.
Project x 1058.02 1000 NPV / Investment 1.05802
Project y 1111.11 1100 NPV / Investment 1.0101

Based on PI we should choose project X has higher PI

Contact us today

Ask for our academic services

Copyright SmartStudyHelp 2016. All Rights Reserved