Marchi Family Inn is a bed and breakfast establishment in a converted 100-year-old mansion. The Inn’s guests appreciate its gourmet breakfasts and individually decorated rooms. The Inn’s overhead budget for the most recent month appears below: Picture The Inn’s variable overhead costs are driven by the number of guests. What would be the total budgeted overhead cost for a month if the activity level is 70 guests?

0

Answer :the total budgeted overhead cost for a month if the activity level is 70 guests = $ 6,620

Working notes for the above answer is as follow

we have been provided with 65guest details of variable cost and fixed cost

Now we will prepate it for 70 guest

activity level: 65 guests Total Per guest
variable overhead costs
supplies 156 2.4
laundry 364 5.6
Toral Variable cost 520 8
fixed overhead costs
utilities 250
salaries and wages 4480
depreciation 1330
Total Fixed Cost 6060
Total Cost 6580

Now we will calculate for 70 Guest

Fixed cost remain same with the change in Guest it will not change only variable cost will change .The calculation for 70 guest is as follow

activity level: 65 guests Total Per guest
variable overhead costs
supplies (2.4*70) 168 2.4
laundry(5.6*70) 392 5.6
Toral Variable cost 560 8
fixed overhead costs
utilities 250
salaries and wages 4480
depreciation 1330
Total Fixed Cost 6060
Total Cost 6620